Brockville mayor addresses concerns over $400K cost overruns in supportive cabins project

Amid ongoing confusion and scrutiny within the Brockville community, Mayor Matt Wren provided a detailed explanation last night regarding the unexpected cost overruns in the supportive cabin project, a regional homelessness initiative .
Speaking at a regular meeting of Brockville City Council on Tuesday April 22, 2025, Wren opened the meeting by addressing concerns from a recent report on the supportive cabins project overseen by the United Counties of Leeds and Grenville (UCLG).
Wren acknowledged the collective disappointment over the additional costs, which have increased from an initial estimate of $500,000 to $900,000, but emphasized that the expenses were justified and had been communicated to the Joint Services Committee as early as December 2024.
“I want to make sure everybody understands, first and foremost, this was not a city of Brockville initiative,” Wren clarified, “It’s a UCLG project, an entirely separate municipal government, and the city has no control or oversight over the projects of other municipalities.”
He elaborated, “Each year, the city of Brockville makes a contribution as a partner municipality towards these regional services, and that contribution totals approximately $4 million a year out of that about 1.1 million of those Brockville tax dollars going to the United Counties annually is dedicated to social housing.”
The mayor stressed that the cabins—intended to house individuals experiencing homelessness—were constructed on a challenging site with bedrock issues that required extensive electrical upgrades, including a new transformer. The extra costs also support the future development of 23 additional housing units on the same property, bringing the total potential capacity to 48 units.
Despite public concern, Wren said the extra funding is being covered by existing housing reserve funds held by the counties, not by resident taxes. Brockville’s only direct contribution will be about $18,000 annually over 10 years to replenish the reserve fund, a share of the broader $4 million counties-held fund.
Wren concluded his address by emphasizing that the original $1 million project was funded through the Ontario Homelessness Prevention Program, and that returning those funds unused would have been a missed opportunity. “I’m kind of happy to see those funds going to good use to put a roof over someone’s head who doesn’t have one,” Wren said.