Parks Canada shares project timeline ahead of Brass Point Bridge closure

With the closure of Brass Point Bridge less than three weeks away, Parks Canada is sharing a timeline and some details on the project, which is expected to continue into December 2027.
As previously reported, the Brass Point swing bridges will be closed to vehicles for about 18 months, according to the federal government. Located in Seeley’s Bay, the bridge spans the Rideau Canal and is scheduled to be fully replaced. The work to replace the bridge will result in subsequent detours for those travelling through the area, as well as area residents, some of whom have previously stated the lack of bridge will cut them off from accessing the City of Kingston – or, at least, doing so in a timely manner.
The bridge is to close on Thursday, Jun. 25, 2026, according to Parks Canada, which oversees the maintenance and operations of the Rideau Canal and its many lock stations. The reopening is “expected” to occur in December 2027, Parks Canada reiterated in a press release issued on Monday, Jun. 8, 2026.
“Parks Canada recognizes the significant impact of this temporary closure for residents, businesses, and travellers,” the federal agency said.
“We are working closely with the contractor to carefully coordinate timelines and minimize the length of the closure.”
The Brass Point bridge project will see both the historic swing and fixed bridges replaced, upgrades to roadway infrastructure, and will “ensure the long-term safety and functionality of this key crossing on the Rideau Canal National Historic Site,” according to the release.
“This significant investment in the community will support reliable transportation infrastructure for residents, businesses, and visitors for decades to come,” Parks Canada stated.
The following is a project timeline as provided by Parks Canada:
Phase 1: Preliminary work (spring 2026 to Wednesday, Jun. 24, 2026) – Bridge remains open to vehicular traffic
Preliminary work will focus on the site preparation activities to support the main construction phase. During this phase, the bridge will remain open to vehicular traffic.
Phase 2: Main construction and closure (Thursday, Jun. 25, 2026 to December 2027) – Bridge closed to all vehicular traffic
The replacement of the bridge structures will require a full closure to all vehicular traffic. A vehicle detour route will be provided. A pedestrian crossing will remain available during construction.
Navigation for watercraft will not be interrupted during hours of operation. Navigation will not be possible under the bridge outside these hours.
Phase 3: Project completion (Late 2028) – Short-term closure required
Final finishing work, including painting of the timber swing bridge, is scheduled for late 2028. This work will require a short-term closure of approximately three weeks to complete the project.
“Parks Canada continues to coordinate with local service providers, including emergency services, to ensure continuity of service during construction,” the release stated, noting that information on the project is updated regularly on the Parks Canada website, and that additional updates will be shared as more information becomes available.
According to the release, area residents can join the “stakeholder list” to receive project updates and/or an invitation to upcoming information sessions by emailing rideau@pc.gc.ca.
“Parks Canada understands how this closure and the resulting detour impacts the daily lives of community members, and we appreciate the public’s patience as we undertake this critical work,” the government agency concluded.